Highway work requiring road/lane/structure closures is planned; however, work may be delayed/canceled due to weather or other issues. Items in italics contain new/updated information. For up-to-date information, call 511 or visit www.511Virginia.org.

DISTRICT-WIDE ACTIVITIES:

Crews will perform various activities throughout the district to include, but are not limited to bridge and guardrail maintenance, brush/tree/limb cutting, pothole/surface/shoulder work, surface treatment operations, work orders, mowing, boom axing, drainage repairs/work and roadside cleanup.

Work at specific locations:

APPOMATTOX COUNTY:

• Note districtwide activities above.

CAMPBELL COUNTY:

• Route 29 N over NSRR, near airportB — bridge and approach work; estimated completion, May 2023.

• Route 29B Timberlake Road intersection Route 622 Waterlick Road — Safety improvement project Lane closures changes in traffic pattern are likely; Starting May 1 with estimated completion May 12, 2023.

• Route 460 Business on Timberlake Road — Signal crew working on advance detection.

• Route 501 – Paving delayed and began June 1 on Route 501 South, between Route 680 Suburban Road to Route 869.

• Route 623 – Road closure. Motorists should expect delays due to a culvert replacement project on Route 623 in Campbell County. Route 623 (Turkey Foot Road) will be temporarily closed from Route 811 (Thomas Jefferson Road) to Route 460 (Lynchburg Hwy). Road closure is rescheduled to begin July 13, 2022.

• Route 682 – Working on a sign project.

• Note districtwide activities above.

CHARLOTTE COUNTY:

• Note districtwide activities above.

HALIFAX COUNTY:

• Routes 501 and 610 – Passing lane project. Use caution during changing road conditions and traffic patterns. 35 m.p.h. at all times during construction. Route 610 connection to 501 closed; one-way detour via Route 610 Murphy Grove Road; estimated to begin June 2022. Fixed completion, May 5, 2023.

• Route 612 (Clays Mill Road) – Rural rustic project.

• Note districtwide activities above.

PRINCE EDWARD COUNTY:

• Route 15 (Farmville Road at Intersection of Routes 133/692 Kingsville Road) – Road construction ongoing with lane closures expected. Road closure of Routes 133/692 Kingsville Road expected to begin June 6, 2022, weather permitting; signed detour in place for about two months.

• Route 702 (Bolden-Flournoy Road) – Rural rustic project.

• Route 730 (School House Road) – Rural rustic project.